A bridge over the Platte River near Schuyler reopened Friday after being closed for about three weeks for emergency repairs, restoring the crossing for residents and farmers in the surrounding area.
The bridge, located at the southern border of Colfax County, reopened at 2 p.m. Friday, according to the Colfax County Sheriff’s Office. The closure had required people traveling between communities on opposite sides of the river to use a detour through North Bend.
The detour affected farmers moving harvested crops from south of the Platte River, including those bringing loads toward Schuyler and other nearby communities. The reopening ended the temporary routing that had been in place since the bridge was closed.
Emergency work preceded planned replacement
The Nebraska Department of Transportation announced the closure on Oct. 28 and said the emergency repairs could take between four and six weeks. The bridge reopened sooner, after roughly three weeks of work.
The structure was built in 1959. NDOT has included it in the agency’s five-year plan under the Nebraska Surface Transportation Program for replacement. The agency said in October that it would reassess the replacement plans after the emergency repairs were completed.
- Location: Platte River crossing at the southern edge of Colfax County near Schuyler
- Reopening: Friday, Nov. 20, at 2 p.m.
- Future work: Replacement is included in NDOT’s five-year transportation plan
The reopening provides access across the river while the bridge remains on the state’s planned replacement list. NDOT’s review of the replacement plans follows the completion of the emergency work.